Flexlink YOUTILIZE Uživatelský manuál Strana 114

  • Stažení
  • Přidat do mých příruček
  • Tisk
  • Strana
    / 125
  • Tabulka s obsahem
  • ŘEŠENÍ PROBLÉMŮ
  • KNIHY
  • Hodnocené. / 5. Na základě hodnocení zákazníků
Zobrazit stránku 113
Providing production
efficiency
Page 114 of 125
Appendix B
Service Monitoring
The following describes what needs to be done for every conveyor in the system.
Initial measuring data
Gap, chain-beam, top
(Gap_top)
The initial (nominal) value must be measured by a service engineer at start up or change of the
component.
Measure_Nominal
Gap_top
Thickness of chain top (Chain_top)
The initial (nominal) value must be measured by a service engineer at start up or change of the
component.
Measure_Nominal
Chain_top
Gap, chain-side plate, idler end (Gap_idler)
The initial (nominal) value must be measured by a service engineer at start up or change of the
component.
Measure_Nominal
Gap_idler
Thickness of tab (Chain_tab)
Formatted: Danish
Zobrazit stránku 113
1 2 ... 109 110 111 112 113 114 115 116 117 118 119 ... 124 125

Komentáře k této Příručce

Žádné komentáře